Transportation of the last components for the concrete towers production

The last segment moulds for the concrete towers of the Peralta I- II wind farm have been loaded in trucks for their transportation to the site. These steel moulds are the remaining components that were located in the port of Montevideo. They will be transported to the site in the following days. Once they arrive to Peralta all the material for the concrete tower mobile production that arrived last December to Montevideo from Natal (Brazil) would be completed.

The transportation of the components to the site has been done meeting specific logistic requisites.

Once the production starts working at full capacity, it will produce about two towers per week and it will employ approximately 150 people among workers, technicians and administrative personnel.