Works begin in Peralta

Since the second week of December the first works on the Peralta I- II Wind Farm are taking place. These works consist of earth clearing in the area where the concrete tower production will be located. The works will stop for at the end of December following the construction calendar and will start again in mid- January. At the beginning of the year, the earthworks will continue and will also extend to the area destined to components’ storage. In addition, it is estimated that at the beginning of February new material and components for the concrete tower production shipped from Natal (Brazil) arrive to the site in Peralta.